WDI Group was engaged by PepsiCo under conditions where conventional project sequencing would not have met the client’s business timeline. The mandate was clear: deliver
a complete workplace build-out faster than any competing firm would commit to.
WDI Group delivered the project in 3.5 months from project start to final delivery — outpacing every competing design firm that had been considered for the engagement.
The strategy that made this possible was unconventional and deliberate. WDI Group secured the demolition permit first and began physical work on site immediately, before
the full building permit had been issued. This sequencing — running demolition-phase activity in parallel with the remaining permitting process — compressed the overall
critical path by weeks. Every subsequent phase was scheduled to recover the time gained at the front end, and to preserve quality, safety, and code compliance at every
stage.
The result was a project delivered not just on time, but significantly ahead of any timeline the client had been quoted elsewhere — without compromise to the workplace
itself.
Across approximately 19,000 square feet, the scope of services WDI Group delivered included Workplace Strategy, Space Planning, Feasibility Studies, Interior Design,
Permit Acquisition, Construction Drawings, Architectural & Engineering, Project Management, Construction, and Furniture Acquisition and Installation. Furniture was
specified and sourced through dedicated vendor coordination, with WDI Group managing vendor negotiation, purchase orders, logistics, and on-site installation through to
completion.
The client response was unequivocal. PepsiCo expressed high satisfaction with both the compressed timeline and the quality of the finished space — a result that reflects
WDI Group’s broader operating principle: speed and quality are not a trade-off when sequencing, permitting strategy, and project management are executed with discipline.
WDI Group managed the entire engagement as the single point of contact — aligning strategy, design, permitting, construction, and furniture procurement under one
accountable team.